09/07/2026
New Roof Installation on James Avenue
The Thomasville Housing Authority (THA) has hired NC Roofing LLC.to install and replace the new roofs on James Avenue.
The replacement of the roofs on James Aveune is in progress. They have completed six (6) buildings and are working to have all installations completed before the Thanksgiving holiday.
We have scheduled roof replacement as listed in the schedule below. Please note that these dates are estimates and may change due to weather conditions or unforeseen circumstances. We will provide updates if the schedule is altered.
- Building 300
- Date Scheduled: 8/10 - 8/13
- Building Task: 2-story
- Pre-Inspections: Done
- Building 304
- Date Scheduled: 8/14 - 8/19
- Building Task: 2-story
- Pre-Inspections: Done
- Building 305
- Date Scheduled: 8/24 - 8/26
- Building Task: 2-story
- Pre-Inspections: 8/25/2026
- Building 309
- Date Scheduled: 8/27 - 9/1
- Building Task: Single Story
- Pre-Inspections: 8/26/2026
- Building 313
- Date Scheduled: 9/8 - 9/10
- Building Task: 2-story
- Pre- Inspections: 9/8/2026
- Building 315
- Date Scheduled: 9/14 - 9/15
- Building Task: 2-story
- Pre-Inspections: 9/11/2026
- Building 317
- Date Scheduled: 9/17 - 9/22
- Building Task: 2-story
- Pre- Inspections: 9/16/2026
- Building 319
- Date Scheduled: 9/23 - 9/25
- Building Task: 2-story
- Pre- Inspections: 9/22/2026
- Building 302
- Date Scheduled: 9/28 - 9/30
- Building Task: Single Story
- Pre-Inspections: 9/25/2026
- Building 303
- Date Scheduled: 10/1 - 10/6
- Building Task: 2-story
- Pre-Inspections: 9/30/2026
- Building 306
- Date Scheduled: 10/7 - 10/9
- Building Task: 2-story
- Pre- Inspections: 10/6/2026
- Building 308
- Date Scheduled: 10/12 - 10/14
- Building Task: 2-story
- Pre-Inspections: 10/9/2026
- Building 310
- Date Scheduled: 10/15 - 10/20
- Building Task: 2-story
- Pre-Inspections: 10/14/2026
- Building 311
- Date Scheduled: 10/21 - 10/23
- Building Task: 2-story
- Pre-Inspections: 10/20/206
- Building 400
- Date Scheduled: 10/26 - 10/28
- Building Task: 2-story
- Pre-Inspections: 10/23/2026
- Building 401
- Date Scheduled: 10/29 - 11/2
- Building Task: 2-story
- Pre-Inspections: 10/28/2026
- Building 402
- Date Scheduled: 11/3 - 11/6
- Building Task: 2-story
- Pre-Inspections: 11/2/2026
- Building 403
- Date Scheduled: 11/9 - 11/11
- Building Task: 2-story
- Pre-Inspections: 11/6/2026
- Building 404
- Date Scheduled: 11/12 - 11/16
- Building Task: 2-story
- Pre-Inspections: 11/11/2026